Oertelsbruch - Rotbutt (Laura)
Many other parts of Thuringia
were involved in the German rocket program. Even before the A4 production had
started in he Mittelwerk the decision was taken to build new engine test stands
close to the production facility. Such a facility here made the final assembly
much easier, because the power-plants did not have to be transported all the way
to Peenemünde for test-firing. Roughly 10% of the engines were
tested.
Gerhard
Degenkolb, Martin Schilling and Bernhard Tessmann had located a slate-quarry
near Lehesten were such a test faciliy could be erected. The slate-quarry was
ideally suited for straight-down-the-wall combustion chamber testing without the
need for flame detectors.
The Oertelsbruch slate-quarry near the hamlet of
Schmiedebach located near Lehesten just to the south of he city of Saalfeld was
the chosen location of the new test facility. Here the so-called Vorwerk-Mitte
was to be erected. The "Steinbruch Verwertungs GmbH" leased the quarry for
170,000 Reichsmark. The head-office of the company was in Atnang-Puchheim.
Besides Dr. Rickhey SS-Sturmbannfuehrer Dr. Fritz Loth was in charge of the
construction and the managing of the project. The SS-Sonderinspektion II under
SS-Hauptsturmfuehrer Gessen supported the project and organized the material and
manpower. Besides the test stands, an underground liquid oxygen plant was to be
constructed. It was a sound decision to also construct a production plant for
liquid oxygen close to the rocket motor test stands. The transport of the liquid
oxygen over larger distances would be eliminated.
The
Oertelsbruch facility mined slate from the side of the mountain for quite some
time. Tunnels were driven into the mountain to mine the slate. The Wifo had
shown an interest in the facility to use the facility for the storage of
important raw materials. According to Wifo documents, the slate quarry belonged
to the "Kuehler Morgen GmbH" in Roettesdorf. Construction begun on September 21,
1943. Manpower came from the concentration-camp Buchenwald. The camp received
the name "Laura". In six month the facility was completed and it received he
code-name "Rotbutt".
When the project was started seven kilometers of
tunnels and 54 halls already existed. Some of these halls 400 square meters in
size were enlarged to 600 square meters. The facility was an open pit operation
190 feet deep with 2 tunnels running into the mountain. The two tunnels were
roughly two meters wide and two meters high. At the point where the slate was
mined, the tunnels reached a height of 15 meters. Seeping water was not a
problem and the rock above the tunnels was very strong. Nearby, quarters for 100
workers were available. The facility had 20.000 sqm of space
available.
In the slate quarry the test stands were erected. The
quarry sides, 40 m high, were to be used to hold the concrete chambers for the
test stands. They were 3.6 m long, 3 m wide, and 4.2 m high with concrete walls
0.4 m thick. The back was open. A steel frame on which the rocket motors were
mounted was located in the front. A large opening in the floor allowed the
rocket exhaust gases to escape. Both chambers were 25 meters apart.
The A4 rocket engines were vertically installed in a
movable steel frame. This arrangement allowed for the quick movement of the
motors. One of the tunnels in the quarry was equipped with 2 tanks holding
alcohol and liquid oxygen. The tunnels, which were approximately 100 m long,
were connected to different side tunnels. Train tracks reached into he
facility.
The huge
underground tunnels and caves were just ideal for the secure production of
liquid oxygen. Lehesten produced 8 tons of liquid oxygen an hour. Production run
for 24 hours a day, 27 straight days without stopping every month. The remaining
days of each month the production was shut down to unfreeze the equipment.
Lehesten produced 5,000 tons of liquid oxygen a month. The facility was handed
over to the Americans by the SS commander of the facility. After the Americans
pulled out the Russians took over.
On July 15, Aleksey Isaev and Arvid Pallo were
dispatched to Lehesten, the site of the A-4 engine firing stand, one of the few
rocket-related facilities, the Soviets found virtually untouched, after the
departure of the Americans. The same month, the top Soviet specialist in rocket
engines, Valentin Glushko was sent to Germany with a group of his associates
from OKB-SD, a design bureau specialized on propulsion systems for
rocket-assisted takeoff for military aircraft. Lehesten became a home for
Glushko's team, where test firings resumed as soon as September 6, 1945. Dr.
Joachim Umpfenbach initially directed the firings, however the same month, V. L.
Shabransky, one of the specialists from OKB-SD, was appointed the director of
the test site, the position he held until Soviet work on rocketry concluded in
Germany in January 1947.
In August the Zentralwerke's V-2 engine static test
stands were back in operation. By December 1945 600 German and Soviet
specialists were at work at Zentralwerk. In March 1946 the first two complete
V-2's were ready for test. At the engine test stands German and Russian
specialists improved the standard V-2 engine for better thrust and performance.
A series of 40 test firings between July and September 1946 used modified
propellant mixer heads and varying mixture ratios. Thrust of the basic V-2
engine had been increased from 25 tonnes to 30 tonnes.
When the Russians left, the entrances were blown in.
It was not until November 20th 1952 that anything happened at the
facility. It was at that time that a GDR company was asked to
clean the mine. In a latter back to the ministry in 1953 the company wrote hat
at least 88 tonnes of steel scrap was still in the mine and that it would take a
lot of money to clear everything out. Nothing was done and it seems that the
scrap is still there.
See also www.slatecity.de









