Reimahg
(Reichsmarschall
Hermann Goering Werke)
One of the most remarkable advancements made by the German
military in World War II was the production of turbine-jet aircraft. The most
famous of these was the Messerschmitt Me 262, developed beginning in 1938 and
fielded in 1944. A special production facility was started in 1944, for quicker
assembly line manufacture. Due to the setup at the main Messerschmitt
factories, fast assembly line production was not possible, and these sites were
vulnerable to Allied bombing. Accordingly, a company called Flugzeugwerke Reichsmarschall Hermann Göring (REIMAHG for short)
was formed as a subsidiary of the Gustloff Werke. Firstly the REIMAHG facility
was to produce the Fw 190 D9, but before production of the aircraft started,
the decision was undertaken to produce the Me 262 instead. The main production
facility, codenamed "Lachs" (Salmon) was located in an old porcelain sand mine in the Walpersberg Hill near
Kahla (south of Jena).
The
construction work on the Großeutersdorf installation started on April 11, 1944.
The plan
for the installation, designed by architect Ernst Flemming, made use of the
already existing tunnel system. The existing tunnel system of the Kahlaer
Porcelain Company was made up of tunnels running in a 90 degree angle to each
other. The tunnels were 3 meter wide and 4 meter high. Two entrances were
leading into the facility.
The old sandpit in the
South-Western part of the mountain was to be incorporated into the overall
concept. The facility was to expand the old system to the West and to the
North. The architect planned the construction of 40 tunnels with a length of
500 meters each.
The first step in the
construction project was the enlarging of the old tunnel system used by the
Kahla AG. The company of Dyckerhoff & Widmann started with the enlarging
and securing of the old tunnel system.
By then construction work at
the Reimahg was in full swing. North of the existing tunnel system, in regular
intervals 12 new tunnels 100 to 200 m in length were driven into the mountain.
The new tunnels were connected by 5 tunnels running in a East-West direction.
Tunnel No. 21, 460 meters in length, was the first tunnel leading through the
mountain in a East-West direction. From this tunnel 53 parallel tunnels were to
be constructed. Connected was the new system by 5 driving tunnels which run
along the length axis of the mountain. The two outside driving tunnels followed
the direction of the mountain escarpment. Twenty-seven entrances created easy access to the facility.
The number of entrances was later increased. Tunnel No. 21 was leading from the
plant to the Reinstädter Valley.
At the end of July 1944 the
architect Ernst Flemming delivered the design to the Reimahg construction
company. The final design showed a facility with altogether 75 tunnels with a
length of 32 kilometers. Seven main entrances were now leading to the Dehna-
and Saale Valley. One entrance led to the North side of the mountain into the
Reinstädter Valley.
The geological assessment was made up by Prof. Deubel in the
nearby city of Jena. The design showed tunnels No. 21 - 36 with a width of 6
and a height of 4 meters. Every tenth tunnel was enlarged to a width of 9 meters.
The side tunnels were used to house the different workshops of the plant.
Kitchen, eating facilities and storage rooms were incorporated into the design.
The tunnel walls were covered with sprayed concrete to keep the dust in the
facility down. All main tunnels were lined and strengthened with concrete. The
tunnel walls of the tunnels designed to house the tool machinery were lined
with bricks, so that the danger of flying dust was minimized.
Again changes
in the design had to be incorporated. Architect Ernst Flemming produced the
second and final design which he delivered to the Reimahg construction company
in December 1944. At this Point in time the construction of tunnels No. 33 - 36
was started. The four huge halls were broken out of the rock to be used as
assembly halls for the Aircraft assembly. The
dimensions of the halls were huge. The
length was to be 180 meters and the width was to be 30 meters. Only two of the
planned four assembly halls were finished. Hall (tunnel) 34 and 35 ended at the
south side of the mountain and were closed by
bunker "O". According to the design, the four halls had a size of 27,000 sqm.
The old tunnel system up to
tunnel 35 was finished, the tunnel system to
the West, tunnels 36 to 74 were not finished by the end of the war. In 1945,
86,400 sqm were available for production. In the eastern part the production of
the Me 262 was begun. The plants 27 entrances were increased to 45 entrances in
the final design. All entrances were marked by roman numerals and they all
ended on the planned road leading around the mountain. On the south side of the
mountain the road was finished. All entrances were between 3.5 to 5 meters
wide. Entrance No. I, often seen in American
photos was equipped with a hoist which was used for unloading material.
Soon seven main entrances were
leading into the plant. Through air photographs, the allies had knowledge of
these entrances. According to the American Air-Force Magazine "Impact" of June
1945, the Americans had known about the
entrances since 1943. As already mentioned, the only entrances in 1943 were the
two in the old tunnel system, which had nothing to do with the Reimahg
facility. Construction work on the underground installation did not start
before the middle of 1944. Because the Americans had spotted the old tunnels of
the Kahla AG, they had no clear picture what happened on the ground, which may
explain why the facility and bunkers were erected without any bombing
attacks.
The first reconnaissance
photos showed what looked like a roadway on the
plateau of the mountain. Construction work at the so-called roadway was by now
finished. What the Allied air photo interpreters classified as a roadway, was
the runway of the plant, where the finished Me 262 fighters were to take off.
The concrete runway was 1,100 meters long and 33 meters wide. On either side of
the concrete landing strip a 45 m wide grass strip was located. The connecting
taxing strip was 15 m wide. According to eyewitness accounts no buildings,
except a wood barrack, were located on the top of the mountain. Some sources
claim that bunkers were built beside the landing strip to fuel the aircraft and
to supply them with ammunition. It was another of the many rumors regarding the
facility. The aircraft were fueled by hand out of fuel drums. Ammunition was
received when the destination was reached.
The runway did not allow any
of the planes to land again which made it impossible to test fly the aircraft.
The start of the aircraft was no
easy undertaking for the pilots.
Rocket assisted starts were the only way to get the aircraft airborne. The
great problem of transporting the aircraft to the top of the mountain, was
solved in a very simple way. Roughly in the middle of the installation just to
the west of bunker 2, was the steep escarpment of the mountain which was used
as a ramp for an inclined elevator. With the help of the elevator the finished aircraft were transported to
the top of the plateau and to the landing strip.
Reconnaissance photos of the
Reimahg, taken on March 19, 1945, showed two Me 262’s
(see photo on top) on the platform of the elevator and one on the bottom of the elevator. Because of these photos taken,
the Allies decided to attack the facility soon.
Because the assembly (bunker 4) halls inside the
mountain could not be finished before production
was getting under way, an emergency solution had to be found. The Reimahg
construction company came up with a fairly simple solution and wooden barracks
were constructed. Three of the four (bunker
1) Reimahg bunkers (workshop 1)
were so erected as wooden barracks, which were surrounded by a wooden casing.
The casing was filled with concrete and in doing so bomb-proof assembly buildings (bunker 2) were constructed. The
idea of creating (workshop 1) these
bombproof buildings (bunker 2) came from
Gauleiter Sauckel. Only bunker "O" was designed
as such.
After the Russians removed all
the machinery and material from the factory, the Soviet commander gave the
order to prepare the underground factory to be blown up. All bunkers (bunker 1) and buildings were blown
up. The dynamiting of the bunkers and buildings took a couple of years to
complete. In the underground plant itself holes were drilled which were to hold
the explosives for blowing up the facility. Luckily the order of the Soviet
commander was not completed.
The Soviet commander decided
not to go through with his plan of blowing up the underground facilities. He
probably saw, that by blowing up the facility the whole mountain would be blown
up, including the nearby village of Großeutersdorf.
After the Soviet troops moved out of the facility nothing happened until
1980 when the East
German Army showed an interest in
the old underground facility. Soon after, parts of
the facility were rebuilt by the East German Army and equipment and ammunition
was stored in the rebuild facility. The new owner of the facility was the 4th
mechanized Rifle Division. The faciliy was now
called Teilelager 1 and was part of the Komplexlager 22 in nearby Rothenstein.
In an emergency situation the depot was to supply the division with everything
what was needed in case of war.
After the
reunification of Germany, the underground depot was taken over by the west
German Army which developed the facility further. The Logistics Brigade East
was now in charge of the depot. For a short time the facility was used to store
old small-arms ammunition of the East German Army. Financial restrains forced
the German Army soon after to close the facility. Now only souvenir hunters
visit the facility illegally and take out what is still left.
Also visit www.walpersberg.de